Timelapse – May 2019, the construction site

3 new caissons immersed and construction of the temporary dike

Three caissons have been immersed, C10, C14 and C15. The belt, which is drawing the new coastline, will be made of 18 caissons. Thirteen are already set up (10 on the west side of the new district, 3 in the east). The belt will be completed by the end of July. In the meantime, a temporary dyke and a road have been built to start to come from land by truck.

Video: SAM L’Anse du Portier